Parallel Factory MES User Guide Overview 日本語

Sample walkthrough: from production to shipping

Using the sample master data and actuals (samples/), this page follows, with diagrams and screenshots, the whole flow from receiving components to making and shipping 10 gear pumps. The detailed operation of each screen is explained on the pages linked at the end of each section.

To get a feel for the flow in motion first, see Factory model: from production to shipping. This page is its detailed companion.

You can reproduce everything on this page yourself. Put the CSVs in samples/master-csv and samples/actual-csv into one ZIP each, and import the master data and then the actuals with Bulk import via ZIP at the top of the screen. Operations not included in the CSVs (completion approval, inspection approval and so on) are listed in the last section.

The sample data values (product names, people's names, customers and so on) are in Japanese, so they appear in Japanese in the screenshots. This page gives them in English, together with their codes.

1. The overall flow

The subject followed here is manufacturing order SMP-FG-001, which makes 10 FG-1000 gear pumps. The housing, the outer part of the gear pump, is made by the upstream manufacturing order SMP-SF-001, which machines a casting and gives it a surface treatment.

From receiving components to shipping, there are the following 10 stages. The roles in charge are separated into horizontal bands (lanes) in the diagram.

Productionpm001 Logisticslg001 Operatorsop001–003 Qualityqc001 1Receivelots 2Orderapprove 3Releaseto WOs 4Dispatchstaff, equip. 5Setupchecks 6Resultsgood, defect 7Approvefinalize 8Inspectpass / fail 9Judgmentapprove 10Shipdeduct stock
Figure 1. The 10 stages and the role in charge of each
Production managementLogistics / warehouseOperatorQuality control / assurance
# Stage Screen used Example on this page
1 Receiving Logistics & Inventory → Receiving 50 castings in lot R3001-260901
2–3 Manufacturing order and release to processes Production & Execution → Manufacturing Orders SMP-FG-001 (10 units) → 3 work orders
4 Dispatching Production & Execution → Dispatching Assigning a worker and equipment to the work orders of SMP-FG-002
5–6 Setup and recording results Work Orders → Setup / Record Results 10 units assembled; 9 good and 1 defective at packing
7 Completion approval Record Results (Approve Production Completion) The 3 work orders become “Approved”
8 Inspection Quality → Inspections Final inspection: flow rate 20.3 L/min, pass
9 Shipment judgment Quality → Shipment Judgments Judged “Approved”, and the judgment approved
10 Shipping Logistics & Inventory → Shipping 5 units to the customer Sample Trading

2. The factory and the people

The sample has one factory, Plant 1 (PL-1). It consists of four levels: factory → line → area → work center, and each piece of equipment, storage location and worker belongs to one of these levels.

PlantLineAreaWork ctr Plant 1PL-1 Machining lineLN-MC Assembly lineLN-AS Logistics, qualityLN-LG Machining areaAR-MC Assembly areaAR-AS Inspection roomAR-QC Shipping areaAR-SH CNC machiningWC-MC1 Pump assemblyWC-AS1 Final inspectionWC-QC1 PackingWC-PK1 Equipment EQ-01, EQ-05Location WIP-01op001 (day), op003 (night) Equipment EQ-02Location WIP-02op002 EQ-03 (CMM)qc001 EQ-04 (vacuum packer)Location SHIP-01lg001 (shipping area) Locations WH-M01, WH-M02 (material warehouse) WH-S01 (spare parts), WH-P01 (product warehouse) People pm001 production, mt001 maintenance
Figure 2. The work center hierarchy (Master Data → Work center) and the equipment, locations and workers belonging to each level
User Role Part on this page
pm001 Production management Registering, approving and releasing manufacturing orders, dispatching, completion approval
lg001 Logistics Receiving components, shipping orders and shipping
op001 / op003 Operator Machining the housing (op003 works the night shift). op001 also enters results for the final inspection of the gear pump
op002 Operator Assembling and packing the gear pump
qc001 Quality control / quality assurance Inspection, shipment judgment

There are two shifts: day shift D (8:00–17:00) and night shift N (20:00–5:00 the next day), which crosses midnight. The shift of an actual is decided by its start time. For details, see Master data.


3. What is made, and how

The FG-1000 gear pump is assembled from the in-house machined housing SF-2000 and five purchased components. The parent–child relationships between products are called the MBOM (bill of materials), and the sequence of processes the routing.

Making the machined housing SF-2000 (manufacturing order SMP-SF-001, 20 pcs) RM-3001Housing casting PR-10 MachiningWC-MC1, std. 25 min PR-20 SurfaceOutsourced (anodizing) SF-2000Machined housing Receiving insp. INS-03 In-process insp. INS-01, 02Conditions: spindle speed, feed Done at the subcontractor Making the FG-1000 gear pump (manufacturing order SMP-FG-001, 10 units) MBOM (per unit) SF-2000 machined housing ×1 RM-3002 gear set ×1 RM-3003 shaft ×1 RM-3004 O-ring ×2 └ alternate RM-3007 O-ring (oil-resistant) RM-3005 hex bolt M6x20 ×4 RM-3006 lubricant ×0.05 L PR-30 AssemblyWC-AS1, std. 30 min PR-40 Final insp.WC-QC1, std. 15 min PR-50 PackingWC-PK1, std. 10 min FG-1000Gear pump Condition: torqueChecklist CL-02 Final insp. INS-04, 05Condition: test pressure Checklist CL-03 Put away WH-P01
Figure 3. Bill of materials (MBOM) and routings. Dashed boxes are outsourced processes; purple text marks when inspections happen
  • The O-ring has an alternate part. RM-3004 (NBR) is normally used, but RM-3007 (oil-resistant FKM) in the same alternate group ORING-P20 can be used instead.
  • Each process of the routing is linked to a work center, candidate equipment, tools, required skills, checklists and manufacturing conditions. For example, PR-10 uses the machining centers (EQ-01 / EQ-05), the end mill TL-01, the skill SK-01 “machining center operation” and the pre-start checklist CL-01.
  • The good units of the final process (PR-50 packing for FG-1000) go into inventory as the product lot.

For how to register MBOMs and routings, see Products, MBOM & Routings in Master data.


4. Receiving components

In charge: Logistics (lg001) Screen: Logistics & Inventory → Receiving

Components delivered by suppliers are registered in the warehouse as lots. All later inventory, consumption and tracing are connected by this lot number.

Receivingregistered by lg001screen / CSV WH-M01 Material warehouse (shelf A-01-01) WH-M02 Material warehouse (shelf A-01-02) WH-S01 Spare parts shelf (shelf M-01-01) R3001-260901Housing casting, 50 pcs R3002-260901Gear set, 50 sets R3003-260901Shaft, 50 pcs Receiving insp. INS-03R3001 appearance → passNo voids or chips R3004-260901O-ring, 200 pcsExpires 2027-08-31 R3007-260901Oil-resistant O-ring, 40Exp. 2028-08-31, alternate R3005-260901Hex bolt, 500 pcs R3006-260901Lubricant, 20 LExpires 2027-02-28 MP-9002-(receipt date)-001Coolant filter, 10 pcsBlank lot number = assigned automatically
Figure 4. Where the received component lots are kept. Rubber products and lubricant have expiry dates
  • You may specify a lot number or leave it blank to have one assigned automatically. The sample specifies numbers for lots that are consumed later (R3001-260901 and so on).
  • Lots with an expiry date appear in the Expiry alerts of the inventory screen as the date approaches. Expired lots can be neither consumed nor shipped.
  • The castings are checked by a receiving inspection (INS-03, visual). The inspection flow is explained in section 7.
The Inventory screen. Component lots, spare part lots, the semi-finished lot SF2000-S001 and the product lot FG1000-S001 are listed with their locations and quantities
Inventory (Logistics & Inventory → Inventory). This screenshot shows the state after importing only 01–15 of the actuals CSVs and finishing shipping: 20 of the 50 castings in R3001-260901 have been used, leaving 30. Spare parts and an additional delivery received at the same time are also listed, and R3001-260902 shows "Defective" because it failed its receiving inspection. MP-9002, whose lot number was not specified, gets a number based on the day it was imported. If you import all the samples, the inventory operations from 16 onward change the quantities (for example, the castings become 31 after a return from issue, and the gear pumps 3 after retained samples)

For details, see Receiving in Logistics and inventory.


5. From manufacturing order to work orders

In charge: Production management (pm001) Screen: Production & Execution → Manufacturing Orders / Dispatching

“What to make, how many, and by when” is registered as a manufacturing order. Once it is approved and released to processes, a work order is created for each process along the routing.

Mfg. order SMP-FG-001 FG-1000 gear pump ×10 Due 2026-10-16 Registered and approved by pm001 (Approve and Expand columns in CSV) Release SMP-FG-001-10PR-30 Assembly, 10 SMP-FG-001-20PR-40 Final insp., 10 SMP-FG-001-30PR-50 Packing, 10 Output lot FG1000-S001Good units of the final process go in as this lot Planned materials (MBOM×10÷(1−1.5%)) SF-2000 10.15, gear set 10.15, shaft 10.15 O-ring 20.30 (alternate OK), bolt 40.61, oil 0.51 L Products not planned cannot be consumed Manufacturing order status Draft Approved Released Completed ApproveReleaseAll approved Work order status Not dispatched Dispatched Started Completed Approved DispatchStartResultsApprove * Work can be started while still "Not dispatched", without dispatching.
Figure 5. Release to processes creates 3 work orders and fixes the output lot and planned materials (top). The statuses of the order and the work orders (bottom)
The details screen of manufacturing order SMP-FG-001. It shows 7 planned materials (planned quantities increased by the standard defect rate, all consumed in step 10) and the 3 work orders created by release to processes
Manufacturing order details. The planned materials and the work orders created by release to processes are listed. The planned quantities are increased by the gear pump's standard defect rate of 1.5%, and every component is used in assembly (step 10). From each row you can go on to setup, result entry and printing the instruction

In dispatching, a worker, equipment and start sequence are assigned to each work order. The worker is checked against the skills required by the routing, and people without the skill, or whose qualification has expired, cannot be assigned (for example, PR-30 assembly requires the skill SK-04 “assembly work”).

The Dispatching screen. Two work orders of SMP-FG-002 are listed as Not dispatched, with worker, equipment and start sequence to choose
The Dispatching screen. In the sample, you can try releasing SMP-FG-002 (approved but not released) from the screen. This screenshot was taken after assigning -10 to op002 and EQ-02, and the other 2 work orders are listed as "Not dispatched"

For details, see Production management and Dispatching in Production execution.


6. Making it on the shop floor

In charge: Operators (op001–003) Screen: Work Orders → Setup / Record Results

Workers open a work order, do the setup and checks, start the work, and record the component lots used and the output. In the sample, the housings are machined on the night shift of 9/1, surface-treated by a subcontractor on 9/2, and the gear pumps assembled on the day shift of 9/3.

9/1–9/2 Night shift N9/2 Day shift D9/3 Day shift D WC-MC1Machining OutsourcedSurface WC-AS1Assembly WC-QC1Final insp. WC-PK1Packing PR-10 Machining good 20 Feed 1350 out of tolerance (deviation) PR-20 Surface good 19, defect 1 (void) PR-30 Assy good 10, 2 alternate O-rings consumed PR-40 Final insp. good 10 PR-50 Packing good 9, defect 1 → 9 units of FG1000-S001 put away in WH-P01 20:000:004:008:0012:008:0012:00
Figure 6. The flow of work over three days. The small gray boxes are setups. The dashed arrow shows the semi-finished lot SF2000-S001 (19 pcs, WIP-02) made by surface treatment being used in assembly
Work (actuals)Inspection processDeviation / defect

The following are recorded for one work order. All of them are entered on the result entry screen (work order list → Record Results).

Record Sample example Meaning
Setup Pre-setup of SMP-SF-001-10, 20:30–20:50 The time taken for setup, and any abnormalities
Checklist CL-01 pre-start check (removing chips is an optional item and left unchecked) It cannot be registered while a required item is unchecked
Material consumption 10 of SF2000-S001, 18 of R3004 and 2 of the alternate R3007 consumed in SMP-FG-001-10 Which lots were used and how many. Products not in the planned materials cannot be consumed. Alternates require a reason
Process condition data Tightening torque 10.2 N·m (in range), feed 1350 (out of range) Checked automatically against the tolerances of the process control items
Output At packing, good 9, defective 1 (DR-05), awaiting rework 1 In the final process, the put-away location (WH-P01) is required
The result entry screen of SMP-FG-001-10. It shows the registered result, 7 material consumption records (including the O-ring with a substitution reason) the work procedure, the instructed process conditions, the process condition data and the status history
Recording results (SMP-FG-001-10, assembly). The list of material consumption keeps the alternate oil-resistant O-ring and its substitution reason

When a work order becomes “Completed”, production management (pm001) checks the results and presses Approve Production Completion. When all 3 have been approved, manufacturing order SMP-FG-001 becomes “Completed”.

Work time (direct and indirect work) and production trouble (a seal failure on the packing machine, safety of the walkway in the assembly area) are also recorded in the sample. For details, see Production execution.


7. Inspecting

In charge: Quality control (qc001) Screen: Quality → Inspections

When an inspection order is issued, the inspection items that match the inspection type, product and process are selected automatically, and the target lot becomes “Awaiting inspection”. Entering measured values checks them against the specification limits and decides pass or fail automatically; when every item is in, the overall judgment is made.

Issue orderitems chosen from criteria Lot "Awaiting insp."consumption, shipping stop Enter resultsvalues checked against spec Judgmentapprove to finalize Pass → lot "Normal" Fail → "Defective" A failure raises a nonconformance automatically Receiving insp. R3001-260901 INS-03 casting appearanceVisual (no spec limits → judged by hand) No voids or chips → pass After judgment the lot returns to "Normal"and can be issued to processes In-process insp. SMP-SF-001-10 INS-01 housing bore (caliper)Spec 49.95–50.05 mm → 50.01, 49.98 49.9550.0050.05 INS-02 housing appearanceNo scratches → pass Final insp. FG1000-S001 INS-04 flow rate (flow meter)Spec 19–21 L/min → 20.3 192021 INS-05 leak test: no leaksOverall judgment pass, grade A
Figure 7. The inspection flow (top) and three of the sample inspections (bottom). The green bars are the specification range, and the purple dots the measured values
The Inspections screen. Four inspection orders are listed, all approved: the receiving, in-process and final inspections passed, and the receiving inspection of the additional delivery R3001-260902 failed
Inspections. All four have been approved. The three inspections in Figure 7 passed, and the receiving inspection of the additional delivery R3001-260902 failed (its lot becomes "Defective"). You can check the measured values and judgment from "Details / results" on each row
  • In-process inspections target a work order (SMP-SF-001-10); receiving and final inspections target a lot.
  • The measuring devices used (DV-01 caliper, DV-02 flow meter) are also recorded. Devices past their calibration date cannot be used for inspection (the sample has one device whose calibration has expired).

For details, see Quality control.


8. Shipment judgment and shipping

In charge: Logistics (lg001) and Quality assurance (qc001) Screen: Logistics & Inventory → Shipping / Quality → Shipment Judgments

A shipment can be carried out only when both the shipping order made by logistics and the shipment judgment given by quality assurance are in place.

① Shipping orderCustomer: Sample TradingFG-1000 ×5, planned 10/16 ② Shipment judgmentJudged "Approved"Target: order + FG1000-S001 ③ ApprovalBecomes ApprovedJudgment doc printable ④ Ship5 units from FG1000-S001Print the slip and ship Checked automatically before shipping 1. The order has an approved "Approved" or special acceptance judgment 2. The lot to ship is usable (status Normal and not expired) FG1000-S001 in WH-P01 9 units → 4 units "Shipped" in the line becomes 5; order done
Figure 8. The four steps of shipping. If the judgment is "On hold" or not yet approved, it stops at ④. "9 units → 4 units" is the quantity at the time of shipping; if you import all the samples, a later retained sample brings it to 3
The Shipment Judgments screen. A judgment of Approved for SMP-SH-001 and FG1000-S001 has been approved, and a judgment of On hold for SMP-SH-002 is not yet approved
Shipment Judgments. Choose the target shipping order and lot, register the judgment, then approve it. In the sample, SMP-SH-002 is left "On hold"
The Shipping screen. SMP-SH-001 to the customer Sample Trading is Completed (FG-1000, ordered 5, shipped 5), and SMP-SH-002 to the customer Sample Industries is still Instructed
Shipping. Carrying out a shipment increases the "Shipped" quantity, and when every line is complete the order becomes "Completed". SMP-SH-002 has an "On hold" judgment, so shipping it stops

In the sample, the shipping orders, shipment judgments and shipments are also imported by CSV (13–15). The shipment number is SMP-SH-001 as specified in the CSV, but the judgment number depends on the day it is assigned, so it varies with the day of import. For details, see Shipping in Logistics and inventory and Shipment judgments in Quality assurance.


9. Tracing afterwards

In charge: Quality assurance (qc001) Screen: Quality → Traceability

All records are connected by lot number, so from a product lot you can follow the components used, and from a component lot the products and shipments it went into.

R3001-260901Castings (received), 20 used SF2000-S001Machined housings (produced), 10 used R3002-260901 gear set 10 R3003-260901 shaft 10 R3004-260901 O-ring 18 R3007-260901 oil-res. O-ring 2 R3005-260901 bolt 40 R3006-260901 lubricant 0.5 L FG1000-S001Gear pumps, 9 unitsFinal insp. pass, grade A Shipped 5Sample Trading4 left in WH-P01 ◀ Trace back: from the product back to the components usedTrace forward: from components to products and shipments ▶
Figure 9. The connections of FG1000-S001. You can go back two levels, to the lot of castings. "4 left" is the quantity at the time of shipping
The Traceability screen. In the trace back of FG1000-S001, SF2000-S001 with R3001-260901 under it, and 6 other component lots, are shown as a tree
Tracing FG1000-S001 on the Traceability screen. The trace back tree shows the same connections as Figure 9

For example, if it turns out that “the castings in R3001-260901 have many voids”, the trace forward of R3001-260901 immediately shows that SF2000-S001 and the gear pump lot FG1000-S001 are affected. Opening the History tab of FG1000-S001 (production, inspection and inventory records) also confirms the 5 units shipped to the customer Sample Trading.

For details, see Traceability in Quality assurance.


10. Trying it yourself

The records imported by the sample CSVs, and those you operate from the screens, are as follows.

Stage Imported by the sample CSVs Operations to do on the screens
Master data The 20 files in samples/master-csv (work centers through users’ skills, maintenance procedures) ―
Receiving 01_receiving.csv (10 component lots and 3 spare part lots, including expired and soon-to-expire lots) Check the expired lots in the Expiry alerts of the inventory screen. If you increase the days to 365, the soon-to-expire lot also appears as expiring soon
Manufacturing orders 02_manufacturing-orders.csv (SMP-SF-001 and SMP-FG-001 released, SMP-FG-002 approved, SMP-FG-003 draft), 17_manufacturing-orders.csv (rework order SMP-RW-001, approved) Release to processes and dispatching of SMP-FG-002 and SMP-RW-001
Execution 03–09 (setups, checks, consumption, output, process conditions), 16_equipment-logs.csv (equipment running, failures and stops) Approve Production Completion for each work order (pm001)
Inspection 10_inspections.csv (4 inspections, up to judgment; the receiving inspection of the additional delivery fails) Approve inspection for each inspection
Shipping 13–15 (2 shipping orders, shipment judgments, shipment; SMP-SH-001 is shipped, SMP-SH-002’s judgment is left on hold) Change the shipment judgment of SMP-SH-002 to “Approved”, approve it, and try shipping
Maintenance 18–20 (3 maintenance plans, 2 spot requests and tool maintenance records; consumables are deducted from inventory). SMP-MT-003, issued from a plan, is left as instructed The maintenance record of SMP-MT-003, issuing orders from the remaining plans, and checking consumption in Consumables monitoring
Tools and calibration 21–23 (TL-01 exceeds 80% of its life and gives a warning, TL-03 is issued and still in use, the expired DV-03 is calibrated) The life warning in Tool Management, and returning TL-03
Inventory and logistics 24–28 (split, move, adjust, status change, scrap, return, return from issue; 2 transfers, 2 pickings, 2 stocktakes; SMP-ST-001 is finalized) Carrying out the transfer and shipping picking left as instructed, entering counts and finalizing SMP-ST-002, and warehouse work progress
Nonconformances and samples 29, 30 (the nonconformance raised by the failed receiving inspection, through scrap to approval; SMP-NC-001 with special acceptance instructed; 2 retained samples) Approving special acceptance of SMP-NC-001, and checking the retention period of the retained samples
Tracing ― Trace FG1000-S001 and R3001-260901 on Traceability

About dates: The work times in the CSVs (9/1–9/3) are recorded as written in the files, but receiving dates, production dates and the dates in assigned numbers become the day of import. For the import rules, see samples/actual-csv/README.md.